Project Time Schedule

Standard

Hi, Following is my time schedule about server view refactor. because I have two exams this week, after that I can spend full time on this project. Thanks

I will go though all the server view files.

June 1 – June 16: Refator following files: (also the included file in PHP)
server_binlog.php server_plugins.php

server_collations.php server_status_monitor.php

June 17 – June 30: Refator following files: (also the included file in PHP)
server_databases.php server_replication.php

server_engines.php server_status_variables.php

July 1 – July 14: Write unit tests for your newly refactored functions.
July 15- July 28: Refator following files: (also the included file in PHP)
server_export.php server_status.php

server_import.php server_status_advisor.php

July 29 – August 11: Refactor following files:
server_privileges.php server_status_queries.php

server_sql.php server_variables.php

August 12 – August 25: server_privileges.php server_status_queries.php
server_sql.php server_variables.php

August 26 – Sept 6: Refator following files: server_common.inc.php server_privileges.lib.php server_variables_doc.php

Sept 7 – Sept 16: Write unit tests for your newly refactored functions.
Sept 16 – Sept 23: Buffers & Some other refator & Final evaluations

About these ads

One thought on “Project Time Schedule

  1. Pingback: Bin Zu: Project Time Schedule | PHP World

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s