Week 13 report (Aug 26~Sept 1)

Standard
  • Key accomplishments last week

In the last week, I finished most of the scheduled tasks.

  • Tasks in the upcoming week

As scheduled,  there are still some works left on this week

1.  multi_submit
2.  server_databases
3.  server_privileges
and add more UT for them.

Week 12 report (Aug 19~Aug 25)

Standard
  • Key accomplishments last week

In the last week, I finished most of the scheduled tasks. refatctor server view pages as well as mult_submit.php and add UT for them.

  • Tasks in the upcoming week

As scheduled,  there are still some works left on this week

I will contact with Marc if there are other urgent works should be finished firstly

1. finish refactoring server_sql.php and UT
2. server_variables_doc.php refactoring and UT
3. other server view pages refactoring and UT

Week 11 report (Aug 12~Aug 18)

Standard
  • Key accomplishments last week

In the last week, I finished most of the scheduled tasks. refatctor server view pages and add UT for them.

  • Tasks in the upcoming week

As scheduled,  there are still some works left on this week

1. server_privileges.php (refactoring and UT).
2. mult_submit.inc.php  (refactoring and UT).
3. refactor server_sql.php

Week 10 report (Aug 03~Aug 11)

Standard
  • Key accomplishments last week

In the last week, I finished most of the scheduled tasks. refatctor server view pages and add UT for them.

1. refactor server_status_queries

https://github.com/phpmyadmin/phpmyadmin/pull/549

2. Uts for PMA_server_status_queries

https://github.com/phpmyadmin/phpmyadmin/pull/556

3. refactor server_variables and related files

https://github.com/phpmyadmin/phpmyadmin/pull/562

4. Uts for PMA_server_variables

https://github.com/phpmyadmin/phpmyadmin/pull/564

  • Tasks in the upcoming week

As scheduled, this week I will refactor the following files:

server_privileges.php (refactoring and UT).
mult_submit.inc.php.

If I still have time, I will refactor
server_sql.php